menu

CRUSH CREEK SUBSTATION

Location: Colinsville, Queensland
Client: UGL Engineering
Status: Completed June, 2018
Capability: Civil Engineering
Sector: Utilities, Energy and resources
Service: Construct Only

The FKG Group was engaged by UGL Engineering to complete the concrete works for the new Crush Creek Substation, which formed part of the network upgrade to integrate new solar farms in the area.

The project scope included 88 bored piers, 770m3 of reinforced concrete foundations, 2.6km of trenching for the earth grid, 2km of conduits, drainage installation, fencing, and the installation of a 16-section 2m diameter oil separator. The contract also included an additional substation at Strathmore, where the team constructed a new transformer slab, installed conduits, earthing, and FRC drainage pipe.

The team adhered to strict environmental procedures to ensure no negative impacts to surrounding areas throughout construction, and overcame several challenges throughout the project, with latent conditions discovered such as hard rock and underground water.

Related projects

  • Clare Substation
    Clare, Queensland

    Located at Clare, 20km west of Ayr in Northern Queensland, the Clare Substation project was one component of a larger effort to construct a new substation in conjunction with Power...

    View full project profile

  • Wandoan Interconnect
    Wandoan, Queensland

    Origin Energy identified a need to construct a conduit for the controlled transfer and meter of LNG from the Surat Basin to Gladstone, as part of the APLNG project. The FKG Group w...

    View full project profile

  • Woleebee CPP
    Woleebee Creek, Queensland

    As part of QGC’s ongoing works to extract coal seam gas (CSG) from the Surat region, they have been constructing a number of central processing plants (CPPs) to aid in processing...

    View full project profile