Toowoomba Hospital Switchboard and Chiller Upgrades

Location: Pechey Street, South Toowoomba, Queensland
Client: Darling Downs Hospital and Health Service
Status: Completed September, 2017
Value: $6 Million
Capability: Construction
Sector: Health
Service: Construct Only

The FKG Group was engaged to perform major switchboard and chiller upgrades of the Toowoomba Base Public Hospital.

Works were completed in an operational environment in two separable portions; the first portion included the chiller upgrade, comprising the supply, delivery, installation, testing, commissioning, and maintenance of the mechanical services, while the second portion comprised of the major switchboard upgrade.

The switchboard upgrade included replacement of the existing Building Energy Management Services (BEMS) main switchboard, new BEMS main switchroom and the Medical Block main switchboard.

Working in an operational environment, the FKG Group team worked closely with service partner NRG Services and hospital staff to ensure minimal impact to operations.