TALINGA POND C

Location: Chinchilla, Queensland
Client: Origin Energy
Status: Completed July, 2015
Value: $14 Million
Capability: Civil engineering
Sector: Energy and resources
Service: Construct only

The FKG Group was appointed to complete the construction of a new 560 megalitre pond, involving expansion of the current brine storage capacity to deal with increases in the associated water by-product of the CSG activities. 

The Talinga Pond C project involved linking a dedicated Interpond Transfer (IPT) system, to the Talinga Pond B and the Talinga Water Treatment Facility.

Working in an existing gas field presented construction challenges. The brine pond was a greenfield site and a heavy level of compliance was required with bulk earthwork activities to meet environmental, quality and safety regulations.

Related projects

  • BEN BOW DAM
    Wallumbilla, Queensland

    As part of their pilot program to develop reserves of Coal Seam Gas (CSG), Santos contracted the FKG Group for the construction of the 200 megalitre Ben Bow Pilot Dam to store wate...

    View full project profile

  • QGC NORTHERN REGIONAL PONDS
    Surat Basin, Queensland

    Utilising Coal Seam Gas sourced from the Surat basin, QGC’s QCLNG project will supply around 8.4 million tonnes of Liquefied Natural Gas (LNG) to the global market every year. As p...

    View full project profile

  • PONGAMIA PILOT POND
    Spring Gully, Queensland

    In 2010, Origin Energy awarded the FKG Group with contracts to carry out the construction of three large water-storage dams as part of their Coal Seam Gas extraction operations. On...

    View full project profile