Location: | Brigalow, Queensland |
---|---|
Client: | Areva Solar KCP |
Status: | Completed September, 2012 |
Value: | $16.5 Million |
Capability: | Civil |
---|---|
Sector: | Energy |
Service: | Bulk Earthworks, Concrete |
The FKG Group was contracted to undertake the site preparation and civil components of the Kogan Creek Solar Boost project across a 30-hectare site.
Works included clearing, grubbing, topsoil stripping, construction of six significant concrete culverts, installation of 1,736 in situ concrete bored piles and associated works, and drainage installation (to interface with existing systems).
The project also involved the construction of solar steam generator pads, perimeter fencing and roadways and required the relocation of 11KVA cables, fibre optic cables and a fly ash pipeline from the middle of the site.